Independent fact-check

Checking the Claims: A Fact-Check of No Spokane Data Center

We checked 34 factual claims on nospokanedatacenter.com against utility filings, county drafts, state law, federal data and local reporting. Here is what holds up and what does not.

Claims and sources checked as of November 15, 2026. Site checked: nospokanedatacenter.com

25 of 34

claims we checked are false, misleading, exaggerated or unsupported.

9 of 34

hold up, and we show those too.

Verdict breakdown: False 6, Misleading 6, Missing context 7, Exaggerated 3, Unsupported or uncited 3, Accurate 9. Total 34.

What the site is fighting

Project
Big Rock (also called Rock Point) Data Center, tied to a proposed hydrogen plant. [6] [7]
Developer
Apricus Energy Partners, via Big Rock Data LLC; CEO Sean Boyd. [6] [45]
Site
514 acres at 11703 W. Medical Lake Highway, West Plains, near Hayford Road. [6] [7]
Requested load
Up to 1,000 MW. Avista's study: about 50 MW by 2030, up to 650 MW by 2033 with $184M in upgrades. [6]
Utilities
Avista (study done, now paused on large data centers) and Inland Power & Light (study requested). [7] [9]
Approvals
None. No permit application; county pause to June 1, 2027; city moratorium to June 2027. [8] [32] [34]
Separate project
An unnamed 500 MW Avista customer near the old Kaiser Mead site, which the site folds into Big Rock. [8]

They say / The record shows

Water use per day

They say

"potential extraction of approximately 10 million gallons per day" and a closed loop "processing 5 million - 50 million gallons per day"

Homepage [1]

The record shows

The site's own Big Rock page says Apricus is pitching 40,000 gallons a day per 320 MW phase, or 80,000 gallons a day at 640 MW full buildout [2]. Other documents show 300,000 to 1.6 million gallons a day [2]. RANGE reports 250,000 to 1 million gallons a day [8]. The 50 million figure was sizing for treating and reinjecting contaminated groundwater, not consumption [2].

Gallons per day

Chart values in gallons per day: site high figure 50,000,000; site headline figure 10,000,000; top of documents range 1,600,000; top of RANGE range 1,000,000; developer pitch at full buildout 80,000.

  • Sources

50 million gallons a day, in context

They say

50 million gallons daily equals "18.25 billion gallons annually"

Homepage [1]

The record shows

Every data center in the United States combined consumed about 66 billion liters of water directly in 2023, about 17.4 billion gallons, per Lawrence Berkeley National Lab [13]. The site's high-end figure for one project would be more than that national total.

Chart values: site figure for one project, 18.25 billion gallons a year. All US data centers in 2023, about 17.4 billion gallons.

  • Sources

Power timeline

They say

"requesting power delivery of 200MW by 2027, 500MW by 2032 with full capacity at 1000MW"

Homepage [1], Big Rock page [2]

The record shows

That was the developer's request, not anything granted. Avista's study found it could deliver about 50 MW by 2030 and up to 650 MW by 2033, and only if the company pays about $184 million. Full 1,000 MW was beyond the study's scope [6]. Avista paused large data center applications in September 2026 for at least 12 months [9]. The county pause runs to June 1, 2027 [32]. Apricus has not filed a permit application [8].

  • Requested (solid line, square markers)
  • Avista study (dashed line, round markers)
Power timeline, in megawatts
SeriesMilestoneMW
RequestedBy 2027200
RequestedBy 2032500
RequestedFull capacity1,000
Avista studyBy 2030About 50
Avista studyBy 2033Up to 650
AnnotationAvista pauseSept 2026
AnnotationCounty pause endsJune 1, 2027
  • Sources

Noise limit

They say

"Noise Cap: Comparable to the Spokane Airport at 65db at the property line."

Homepage [1]

The record shows

No 65 dB cap has been adopted. Washington law (WAC 173-60-040) already limits industrial noise reaching homes to 60 dBA by day and 50 dBA at night; 65 applies only to noise going into commercial property [16]. The county's draft ordinance is stricter: 50 dBA at the nearest property line, plus a low-frequency (dBC) limit tied to pre-construction background noise [11].

Decibel ruler: 65 is the site claim. 60 dBA is state law for daytime noise into homes. 50 dBA is state law for nighttime noise into homes and the county draft limit at the property line.

  • Sources

Kalispel Tribe

They say

"1,500 people on the Kalispel Tribe and more in the greater Spokane area affected with Plume"

Homepage [1]

The record shows

The Kalispel Tribe has 470 enrolled members, its reservation is 55 miles north of Spokane, and it holds 40 acres of trust land in Airway Heights [20]. The tribe rejected the gas-fired facility Apricus pitched for its land [6]. No plume model has been published.

Site claim: 1,500 people. Tribe's enrolled membership: 470.

  • Sources

Every claim we checked

Filter by verdict or topic, search the text, and open any card for the record and its sources.

Showing 34 of 34 claims

Where they have a point

A fair check cuts both ways. These concerns are real and sourced.

The scale is real.

1,000 MW is about Avista's entire average hourly load, and RANGE puts it at about two-thirds of Avista's generating capacity. [9] [44]

The developer is unproven.

No completed project, a home address as headquarters, a dead Livermore pitch, a Kalispel rejection, and no public answer on financing. [6] [8]

The transparency complaint holds.

Commissioner Al French talked with Apricus for over a year without disclosing it and offered Boyd a chance to edit his letter to the Legislature. [7] [8]

On-site gas power is the under-told risk.

The site's documents show a Tenaska gas supply of about 50,000 MMBtu a day from 2028, and Apricus has looked at Siemens SGT-800 turbines, which would need air permits. [2] [44]

Water stress is real.

A Spokane River reach went walkable in August 2025, the West Plains has serious PFAS contamination in private wells, and the site sits on a critical aquifer recharge area. [8] [23] [27]

Ratepayer protection is still a promise, not law.

A large load bill (HB 2515) did not pass, and the state utility commission's policy proceeding is still open. [9] [10]

Permanent jobs are few.

State data shows 53 permanent jobs against about 300 temporary ones under the urban data center tax break. [28]

The county's own draft rules already answer several of these fears: a 1,000 foot setback from homes, 50 dBA at the property line, no cooling water from private wells, a water use cap of 0.3 liters per kWh, and a decommissioning bond [11]. Scaling the draft's own 20 MW example (13.9 million gallons a year) to 650 MW gives a ceiling of about 1.2 million gallons a day from potable sources. That is our calculation from the draft, not a county figure.

Claims rated Accurate

Methodology and limits

How we checked

We read every page of the site: home, Big Rock, Dangers, Defined, Locations, News and Call to Action. Each factual claim was checked against primary records first (Avista, the Washington Utilities and Transportation Commission, Spokane County drafts, state law, EPA, USGS, Lawrence Berkeley National Lab, JLARC), then local reporting. Opinions, event listings and candidate endorsements were not graded.

Verdicts

False means the record contradicts it. Misleading means technically sourced but framed to give a wrong impression. Missing context means true in part but leaving out facts that change the meaning. Exaggerated means the direction is right but the size is overstated. Unsupported means no source is given and none was found. Accurate means the record backs it.

Limits

The county has posted a newer draft ordinance than the August 14, 2026 version used here, so its numbers may change. The Avista study and developer emails are known only through public records requests, as reported by the Spokesman-Review, RANGE and the site itself. Claims and sources checked as of November 15, 2026.

Credibility note

The site's Call to Action page carries leftover template text under Council Member Kate Telis saying the group is working to protect our oceans [46].